Calgary Jeep Association

Author Topic: Waiparous trail project - October 22nd  (Read 11080 times)

0 Members and 2 Guests are viewing this topic.

Offline AstraX

  • That CB Yapper
  • Posts: 863
Re: Waiparous trail project - October 22nd & 23rd (tentative)
« Reply #15 on: October 08, 2016, 01:26:49 PM »
I am just updating this to confirm it is going to be the Oct 22/23rd weekend.

It sounds like we will be decking a couple of bridges and willow staking the banks around them.  If I am understanding correctly we will be between points 77 & 87 on the map.

Let me know if you are going to be able to make it so I can give them some kind of number.

Thanks

Offline morerpmfred

  • Talks waaay too much!
  • Posts: 1604
Waiparous trail project - October 22nd & 23rd (tentative)
« Reply #16 on: October 08, 2016, 05:26:25 PM »
Perfect. What type of fasteners for the bridge decking? Regular deck screws from Rona?????
18v impactors enough ?
Bring generator for power tools and charge batteries?

Offline rws

  • CJA Members
  • Talks waaay too much!
  • Posts: 1543
  • Stump Grinder
Re: Waiparous trail project - October 22nd & 23rd (tentative)
« Reply #17 on: October 08, 2016, 05:59:43 PM »
In.

Offline AstraX

  • That CB Yapper
  • Posts: 863
Re:
« Reply #18 on: October 08, 2016, 08:15:16 PM »
Need to confirm if we need to bring anything.   I will let you know.

Sent from my SM-G935W8 using Tapatalk

Offline rws

  • CJA Members
  • Talks waaay too much!
  • Posts: 1543
  • Stump Grinder
Re:
« Reply #19 on: October 15, 2016, 09:56:33 PM »
Need to confirm if we need to bring anything.   I will let you know.

Sent from my SM-G935W8 using Tapatalk
Is this a "go"?  What to bring,etc.?

Offline AstraX

  • That CB Yapper
  • Posts: 863
Re:
« Reply #20 on: October 16, 2016, 11:13:20 AM »
It is.

The plan is to have all the work done on the 22nd so just one day.

He said the only tools we need will be big hammers to drive the spikes in for the decking, and planting bars(like tree planters use) to make holes for the willow sticks.

Below are the responses I have received from the volunteer coordinator.

"Hi Dan,

If you have any planting bars or heavy duty hammers, you can bring them for sure. We will be using galvanised spikes to deck the timber bridges. I think if there is enough of us, we should be able to get both bridges decked and some willows planted by the end of the 22nd. I don’t plan on being there on the Sunday."

 "Hi Dan,

Just wanted to touch base with you about the potential project on October 22nd. The location of the work sites will now be on the main GhP4 road system, and we will be working on both of the new timber bridge that cross Lost Knife and 4 Mile creek. The work will involve decking the bridges as well as willow staking the banks. Let me know if you have any questions or concerns. As far as timing goes, we can aim to be at the south Ghost Staging area for 9-930am."





Sent from my SM-G935W8 using Tapatalk

Offline morerpmfred

  • Talks waaay too much!
  • Posts: 1604
Re: Waiparous trail project - October 22nd
« Reply #21 on: October 16, 2016, 10:52:16 PM »
Perfect. Thanks Dan. How about we leave a&w parking lot in Cochrane for 8.30 Saterday morning.
Have lots of hammers. Even some bfh. But whats a planting bar?

Offline MattMan

  • Administrator
  • That CB Yapper
  • Posts: 704
  • old age & treachery wins over youth & vigour
Re: Waiparous trail project - October 22nd
« Reply #22 on: October 17, 2016, 12:47:19 AM »
It is.

The plan is to have all the work done on the 22nd so just one day.

He said the only tools we need will be big hammers to drive the spikes in for the decking, and planting bars(like tree planters use) to make holes for the willow sticks.

Below are the responses I have received from the volunteer coordinator.

"Hi Dan,

If you have any planting bars or heavy duty hammers, you can bring them for sure. We will be using galvanised spikes to deck the timber bridges. I think if there is enough of us, we should be able to get both bridges decked and some willows planted by the end of the 22nd. I don’t plan on being there on the Sunday."

 "Hi Dan,

Just wanted to touch base with you about the potential project on October 22nd. The location of the work sites will now be on the main GhP4 road system, and we will be working on both of the new timber bridge that cross Lost Knife and 4 Mile creek. The work will involve decking the bridges as well as willow staking the banks. Let me know if you have any questions or concerns. As far as timing goes, we can aim to be at the south Ghost Staging area for 9-930am."





Sent from my SM-G935W8 using Tapatalk
I'm in!



Sent from my iPhone using Tapatalk
MattMan

'21 JL Rubi, 3.6l 8spd, Warn VR10, 2.5" lift, Tazered w/35’s

Offline MattMan

  • Administrator
  • That CB Yapper
  • Posts: 704
  • old age & treachery wins over youth & vigour
Re: Waiparous trail project - October 22nd
« Reply #23 on: October 17, 2016, 12:50:46 AM »
Perfect. Thanks Dan. How about we leave a&w parking lot in Cochrane for 8.30 Saterday morning.
Have lots of hammers. Even some bfh. But whats a planting bar?
Not familiar with Wiaporous area (yet), so Cochrane A&W works for me and can follow you out!


Sent from my iPhone using Tapatalk
MattMan

'21 JL Rubi, 3.6l 8spd, Warn VR10, 2.5" lift, Tazered w/35’s

Offline AstraX

  • That CB Yapper
  • Posts: 863
Re: Waiparous trail project - October 22nd
« Reply #24 on: October 17, 2016, 05:17:28 PM »
Perfect. Thanks Dan. How about we leave a&w parking lot in Cochrane for 8.30 Saterday morning.
Have lots of hammers. Even some bfh. But whats a planting bar?

Just got an update that the crews working on the bridges have gotten ahead of plan.  We will just be planting willows so no hammers are needed.

As far as a planters bar, what I have pictured it as is like an ice bar with the pointy end.  I could be completely wrong, but I think its for you to stab a hole in the dirt to insert a willow bough.

Offline EEP

  • UberWheeler
  • Posts: 328
Re: Waiparous trail project - October 22nd
« Reply #25 on: October 20, 2016, 10:03:52 AM »
I will be there, see you guys Saturday morning
01 XJ, RE 3.5" lift, Smittybilt XRC front & rear bumper, X2O 8,000 lb winch, 33" MT/R's
, ARB snorkel, lockers and a bunch of other stuff
06 TJ, 2" lift, 31" Goodyear Territory's.
14 JKU, wife's urban 4X4.

Offline hps4evr

  • Administrator
  • Talks waaay too much!
  • Posts: 2959
Re: Waiparous trail project - October 22nd
« Reply #26 on: October 21, 2016, 10:51:09 AM »
Just got an update that the crews working on the bridges have gotten ahead of plan.  We will just be planting willows so no hammers are needed.

As far as a planters bar, what I have pictured it as is like an ice bar with the pointy end.  I could be completely wrong, but I think its for you to stab a hole in the dirt to insert a willow bough.

Do we know what trails are being repaired?
YJ=Y’all Jealous

Offline Jrama

  • That CB Yapper
  • Posts: 923
Re: Waiparous trail project - October 22nd
« Reply #27 on: October 21, 2016, 12:56:04 PM »
I will be there as well, I am camping in waiparous tonight, so I would need to know where to meet everyone.

Offline morerpmfred

  • Talks waaay too much!
  • Posts: 1604
Re: Waiparous trail project - October 22nd
« Reply #28 on: October 21, 2016, 03:21:01 PM »
Ghost staging area. A mile or so before the lost knife trail head. On the left side of the forestry trunk road.

Offline AstraX

  • That CB Yapper
  • Posts: 863
Re: Waiparous trail project - October 22nd
« Reply #29 on: October 22, 2016, 06:11:14 PM »
How did it go today?  I got hit with something this morning and was in no condition to leave the house.